Post by burnit »

Hello,

we are testing Scheduler Pro and have a specific question.

Our company is usually closed on weekends.
But sometimes we produce on Saturday on some resources.

Is there any way to schedule them during non-working hours without changing the times of the resources we don't produce on weekends?

Thanks a lot!
Andre


Post by mats »

we are testing Scheduler Pro and have a specific question.

We're glad to hear :)

Is there any way to schedule them during non-working hours without changing the times of the resources we don't produce on weekends?

You can assign exceptions to your resource calendar and you can also use the https://bryntum.com/products/gantt/docs/api/SchedulerPro/model/EventModel#field-ignoreResourceCalendar flag to indicate to ignore resource calendars for a certain event.


Post by burnit »

Thanks for your quick reply.
Do you have an overview of all exeptions i can assign to my ressource calendars?

Many thanks.
André


Post by marcio »

Best regards,
Márcio