Hi,
I set the parent task end date as 2023-09-25 manually, but it doesn't effect. The chart shows it as 2023-09-23.
If I say end date is 2023-09-25, it means that the task must be finished before 2023-09-25. If so yesterday, on 2023-09-24. But it is weekend. So the Chart automatically sets the first working day which is 2023-09-23, doesn't it?
I've shared the JSON and screenshot as attachments.
Thanks.