Hi,

On creating an invalid dependency between 2 tasks, we notice that the color of the circle is green even though the tooltip says invalid.

green_circle_for_invalid.png
green_circle_for_invalid.png (30.07 KiB) Viewed 158 times

Steps to reproduce:

  1. Go to Bryntum gantt advanced example ( https://bryntum.com/products/gantt/examples/advanced/ )
  2. Create dependency from 1.1.4 Configure Ports to 1.1.5 Run tests by hovering over the successors task instead of circle
  3. The circle appears green

Can we show the red circle on hovering over the invalid task?

Thanks,
Rayudu.


Post by alex.l »

Hi Rayudu,

Thank you for the report! I've reproduced that and opened a ticket. Here is a lick to track the status https://github.com/bryntum/support/issues/5709

All the best,
Alex