We purchased Gantt View Pro for Odoo v 15.0 https://apps.odoo.com/apps/modules/15.0/bryntum_gantt/
There are some bugs in the functionality:
- When we set the START dates and then refresh the page, it automatically resets those dates to Jan 2, 2023 – it’s a project start date
- When we set ASSIGNED RESOURCES from the Gantt View, it does not synchronizes with tasks and Assigned resources of the task from the project view still empty