Post by moblitas »

Dear Support,

I have tried to export to MSP file but the duration still in zero I have replied into bryntum odoo

https://snipboard.io/RTceYL.jpg

https://snipboard.io/w1oCl5.jpg

Thanks for your support

Milton


Post by arcady »

Which version of MS Project do you use? We also need more details on the dataset to reproduce this or steps how this can be reproduced.

Like 1) make a task, 2) assign a resource etc. No need for many tasks I think.


Post by moblitas »

Hi,

Currently i am using: Microsoft® Project® Online Desktop Client MSO (Version 2302 Build 16.0.16130.20298) 64-bit

I have used your site to reply that and I have completed the task with duration and resources and it works as I show in the follow link

https://snipboard.io/aiq5vl.jpg

But when I define task without resource and with duration the export option change its as milestines (zero duration) in to MS Project, I think it should be a issue

https://snipboard.io/2akHqz.jpg

https://snipboard.io/3QwIEJ.jpg

Best regards


Post by arcady »

But when I define task without resource and with duration the export option change its as milestines (zero duration) in to MS Project, I think it should be a issue

Well export feature doesn't change durations itself. It's just MS Project treats the exported data the way it wants.
The data model of the Gantt is a bit different than the MS Project has. And we just don't provide all the data MS Project needs apparently.

So this happens for tasks without assignments - ok. And what scheduling mode do they use? This can be checked on the "Advanced" tab on the task editor.