Support Forum
In Ms project, the defaultAvailability of "24 Hours" calendar is [00:00-00:00], after a .mpp file is imported into Bryntum gantt. Duration [00:00-00:00] is considered to be zero.
Seems it can work after I update [00:00-00:00] to [00:00-24:00]. But support [00:00-00:00] need to be supported as well since it's a valid availability duration in MS project.
Seems it can work after I update [00:00-00:00] to [00:00-24:00]. But support [00:00-00:00] need to be supported as well since it's a valid availability duration in MS project.
Thank you very much for reporting. The ticket is here:
https://app.assembla.com/spaces/bryntum/tickets/9272-ms-project-importer-wrongly-interprets-duration--00-00-00-00--as-zero/details
https://app.assembla.com/spaces/bryntum/tickets/9272-ms-project-importer-wrongly-interprets-duration--00-00-00-00--as-zero/details
Here it is: https://github.com/bryntum/support/issues/6474