We are noticing that constraints are added in to the Program based around some task movements, so there are gaps occurring in the program.
What we are after is how we can disable constraints globally or on a per task basis. We are looking at this from the point of view of MS Project whereby constraints are either turned on or off, it appears that constraints are automatically enabled based around a set of conditions that can occurs with tasks.
What we are after:
Ability to globally not have constraint dates sent
or
Ability to constraint date to be set to on or off in Project
or
Ability for constraint date to be set on or off on a Task
We are after the same functionality as project where constraint date can be turned on and off on demand, constraint is creating issues for us scheduling tasks when they are lengthened or shortened.