Hi,
I have the following business requirement. I have tasks/events that might span over many days, assigned to resources with calendars that have non-working intervals. These tasks consume and generate stock material. So I need to determine how much stock will be consumed and generated during certain time periods (for example, during each day, assuming the tasks span over several days).
To do so, is there a easy way to determine either the task subintervals dates (when it stops for a non-working period and then resumes work) or the active time of task over a period (like hours worked during Monday)?
Any other ideas?
Thanks