Hi Team,
We have been using the premium licenses for bryntum for about 6 months now but are facing some bugs and technical challenges with both bryntum gantt and calendar how can we setup a call with the bryntum team to get those resolved?
For this one: viewtopic.php?t=24133
Can you please upload a full test case we can run and debug?
Re viewtopic.php?t=25133, I just replied - you can perhaps upload the data on a file sharing service and provide us the link?
we also want to discuss and understand how bryntum calculates critical tasks and the critical path
I'll ask a colleague to chime in on this.
we also want to discuss and understand how bryntum calculates critical tasks and the critical path
For general concept of the critical path method please see this article: https://en.wikipedia.org/wiki/Critical_path_method
The feature basically goes through the project tasks starting from the project end date and collects critical tasks (task has critical field indicating if its critical)
mats wrote: ↑Tue May 30, 2023 3:17 pmFor this one: viewtopic.php?t=24133
Can you please upload a full test case we can run and debug?
We are facing some issues with the test case, a colleague of mine is currently updating that thread with his findings
We also want to understand the following :
if the tasks of a particular schedule are not manually scheduled do some sort of calculations also happen for task dependencies?
If yes, then will manually scheduling all the tasks in a schedule just disable those calculations for dependencies and just show us the default dependencies from the dependency data we push into bryntum?
The reason i am asking this is because i want to understand, if the later is true will it also remove the cyclic dependency issue we get since bryntum is not going to calculate anything and will only render the data
The feature basically goes through the project tasks starting from the project end date and collects critical tasks (task has critical field indicating if its critical)
so that means bryntum does not do any kind of calculations to figure out if a task is critical or not, correct?
It simply takes the value of critical from the data we provide
No, we calculate it and you can read the critical
field value to learn if a task is critical or not.
Note it's readOnly https://www.bryntum.com/products/gantt/docs/api/Gantt/model/TaskModel#field-critical