Post by jptheissen »

I am new to the project and have been asked to solve an issue we've been facing in regard to how lag days are applied.

Issue:
The current defaults of Night Shift, Alldays, and Business allow to choose whether days are calculated using Weekdays only or to include Saturday and Sunday as well.

On top of that you can add Lag days that follow the same format, however there doesn't seem to be an option to configure one setting to calculate for Business Days only for scheduled days, but have the Lag days follow the everyday schedule.

As of now the Lag days and the Scheduled days are required to follow the same format, but I need a format that allows a hybrid option.

If you could point me in the direction of where to look, or give me more insight on how I could Achieve this, I would really appreciate it.


Post by mats »

Sounds a bit similar to this request, does this match your requirements? https://github.com/bryntum/support/issues/6926