Hello, I was wondering if it is possible for me to pull the start date of my task to as soon as possible, respecting the dependency.
For example, I have 2 tasks, A and B. A starts on January 1st and B starts on January 5th. I create a dependency where task B should start 1 day after the end of task A.
I would like task B to be dragged to the first day it can start after this dependency is created.
My constraint type is now "startnoearlierthan".
Hey produto,
Thanks for reaching out!
Could you provide more clarification regarding that? Do you want to move the task automatically when you create the dependency? Or are you not able for some reason to achieve the behavior that you mentioned?
Are you able to reproduce the behavior that you want in our demo here? https://bryntum.com/products/gantt/examples/basic/
For example, I have these two tasks:
- tasks.png (20.48 KiB) Viewed 110 times
When I add a FS Dependency with a 1 day lag, it looks like this:
- dependency.png (4.54 KiB) Viewed 110 times
)
But when I add a FS Dependency, I want the successor to be dragged like this:
- dragged.png (13.92 KiB) Viewed 110 times
I want the successor to be dragged automatically to the minimum start date. In the case above, the minimum is 1 day after the end of the predecessor (task 1)