Post by julius.98 »

Hello,

after testing the gantt module I found out that the milestones created within the gantt view are not linked with the milestones that can be configured in the project itself through the project updates (accessable through the project status that can be seen on the top left in the task overview). It would be great if the milestones would update each others in the project update and in the gantt view (just like the tasks do) so that you do not have to set up all milestones twice.

Thank you in advance!

Best regards, Julius


Post by usamagull »

hi Julius,
We are looking into the issue, we'll let you know shortly.


Post by julius.98 »

Hello,

has there been any update on this issue? Thanks.

Best regards, Julius


Post by mats »

Not yet I'm afraid.