Last question: when clicking on "Project start" and "Project end" vertical line, is that possible to trigger a custom action ?
Can you provide a quick react example ?
We were able to set the vertical lines for the start and end of the project applying the strategy that you indicated us.
...
projectLinesFeature: true, // looks like it forces magnetism
...
<BryntumGanttProjectModel
//...other props
startDate={'2019-01-01'}
endDate={'2019-01-10'}
But we are getting an "unexpected behavior", despite having set the dates for the vertical lines, they automatically move to the start of the leftmost task and the end of the rightmost task for start line and end line respectively.
Is there a setting to prevent them from being automatically positioned? and strictly follow the dates passed to BryntumGanttProjectModel?
Looks like you have a lot of automations with that. How could we simplify display horizontal marker with react bryntum gantt, with no "blakc magic" happening function of them ?