Hello Bryntum Support Team,
I need clarification on the behavior of task start date changes in Bryntum Gantt. Specifically, I would like to understand when and why task start dates can be changed and why sometimes they cannot be changed, depending on the order in which changes are made.
Here are some scenarios I've observed:
1. Changing the start date of task "1 Setup web server" to a past date:
* Sometimes, only "1.1 Data center server setup" moves.
* Other times, only "1.2 Install Apache" moves.
2. Changing the start date of "1.1 Data center server setup" to a past date:
* Sometimes, this causes "1 Setup web server" to move as well.
3. Changing the start date of "1.2 Install Apache" to a past date:
* Sometimes, this causes "1 Setup web server" to move.
I need to explain this behavior to end users, so it would be very helpful to know the following:
* Why does this happen?
* Under what conditions can these changes be made, and when can they not?
* How does the order of operations affect the ability to change start dates?
I tried the example provided in this link:
https://bryntum.com/products/gantt/examples/advanced/
Thank you for your assistance!