Post by maz_odiy »

Hi there

We have an employee that doesnt work on Fridays and has a different calendar to the default - however the Gantt is not recognising this?

We have even specified the calendar on the task line but it still doesnt recognise the nonwork day (friday).

Any ideas?

Cheers
Maz

Attachments
EmployeeCalendarSetup_noFriday.png
EmployeeCalendarSetup_noFriday.png (156.34 KiB) Viewed 33 times
gantt_calendar_issue.png
gantt_calendar_issue.png (228.67 KiB) Viewed 33 times

Post by nivl »

Hi Maz,

Yes, have you, by chance, put the calendar on the person in question on their employee profile but not on the task that's supposed to adhere to the 30 hour week?

The reason I'm asking is the Gantt doesn't read individual calendars set on employees but rather reads the global calendar set on the Gantt View Pro settings and the calendar set for individual tasks on 'Calendar' in the advanced tab. The latter is where you'd select the 30 hour calendar for the employee, which should then translate to a correct depiction on the Resource Utilization. See example in attached screenshots.

Please let me know if this solves the problem.

Attachments
Altered Cal in Working Schedules.png
Altered Cal in Working Schedules.png (99.96 KiB) Viewed 29 times
Calendar on Advanced Tab.jpg
Calendar on Advanced Tab.jpg (522.02 KiB) Viewed 29 times

Niels