Hi Team,

I wanted to understand the expected behavior of how the rendered gantt is decided when exporting a PDF with Date Range value in Schedule Range.

Lets say I am at hour level zoom and I export a date Range of one month then the exported PDF has very long rows to fit the entire gantt at hour level zoom, but when I am at year level view, and I export one one, I still see multiple years of gantt which fall outside the date range. It does not seem like consistent behavior. Is this a bug?

Attachments
Gantt - 2026-11-04T160202.683.pdf
(169.03 KiB) Downloaded 27 times
Gantt - 2026-11-04T160135.979.pdf
(220.75 KiB) Downloaded 21 times
Screenshot 2026-11-04 at 4.02.10 PM.png
Screenshot 2026-11-04 at 4.02.10 PM.png (151.07 KiB) Viewed 237 times

Post by ahmadzaheer »

Hello,

Thanks for reaching out.

In the current implementation, it is intended. When exported with the date range, we take the current view preset.

We have opened a feature request to include a drop down along with the date range to select the view preset in the print dialog. We will evaluate this. Please subscribe to the ticket to get the latest updates on it.

https://github.com/bryntum/bryntum/issues/14128

Regards,
Ahmad Zaheer