Hello,
I need your help again with the dates as I'm having different combination of problems, I'm using the version 4.0.2 with the attached json:
- Research 1 task is flagged as manual and scheduling Normal and the end dates gets recalculated from 16/feb to 15/feb for no reason, if it's manually scheduled and Normal the dates should not change right?
- Research 2: Changing the calendar from business to general turns the duration to 12 days with the same dates, this is not based on effort so why the duration gets calculated as 12 days if it's only 5 days?
- Research 3: Using the business calendar but putting the start on 8am and end 17 (which matches the business calendar) gets the duration calculated as 4.9, but it's using the full business day, so why is not getting calculated to full day?
- Meeting 1 is using start date and end date with the same date and gets it flagged as milestone, 0 duration, which make sense as it's 0 hours... so in order to do a 1 day task I've changed to...
- Meeting 2: start on 8am and ends on 17, which is a full day work based on the business calendar, but the duration is now 0.8 days (I think it's the same as the item 3)
The above are happening after changing the project calendar to business as suggested here: viewtopic.php?f=52&t=15717 if I change the project calendar back to general then the errors are similar to the other post we have created
We are welcome to suggestions as our project is getting delayed quite heavily,
Thanks,