Post by rahulranjan »

Hi

  1. For the Below Task (Event1) if i define night calendar the effort for 1 day should be 8 hours but it o/p 24 hours which is default , calendar is not taken into consideration. ? If Duration is 2 then effort should be 2* 8 = 16 hours . It should be based on calendar.
  2. I have defined a calender of 8 hours per day i.e night calendar so if the task duration is 1.
    Start Date is :Tue Dec 01 2020 00:00:00 GMT+0530 (India Standard Time)
    then
    End Date is :Fri Dec 02 2020 00:00:00 GMT+0530 (India Standard Time)
    should be the above
    But it gives
    start Date is :Tue Dec 01 2020 00:00:00 GMT+0530 (India Standard Time)
    End Date is :Fri Dec 04 2020 00:00:00 GMT+0530 (India Standard Time)

Why ?


import { GanttProjectMixin } from "./lib/Engine/quark/model/gantt/GanttProjectMixin.js";

const project = new GanttProjectMixin({
  eventsData: [
    {
      id: "e1",
      name: "Event1",
      startDate: new Date(2020, 11, 1),
      duration: 1,
      calendar: "night",
      manuallyScheduled: false
    },
    {
      id: "e2",
      name: "Event2",
      startDate: new Date(2020, 11, 1),
      duration: 1,
      calendar: "business",
      manuallyScheduled: false
    }
  ],
  calendarsData: [
    {
      id: "general",
      name: "24 Hour Calender",
      intervals: [
        {
          recurrentStartDate: "on Sat at 0:00",
          recurrentEndDate: "on Mon at 0:00",
          isWorking: false
        }
      ],
      expanded: true,
      children: [
        {
          id: "business",
          name: "6 Hour Calender",
          hoursPerDay: 6,
          daysPerWeek: 5,
          daysPerMonth: 20,
          intervals: [
            {
              recurrentStartDate: "every weekday at 12:00",
              recurrentEndDate: "every weekday at 13:00",
              isWorking: false
            },
            {
              recurrentStartDate: "every weekday at 17:00",
              recurrentEndDate: "every weekday at 08:00",
              isWorking: false
            }
          ]
        },
        {
          id: "night",
          name: "Night shift",
          hoursPerDay: 8,
          daysPerWeek: 5,
          daysPerMonth: 20,
          intervals: [
            {
              recurrentStartDate: "every weekday at 6:00",
              recurrentEndDate: "every weekday at 22:00",
              isWorking: false
            }
          ]
        }
      ]
    }
  ],
  dependenciesData: []
});

await project.commitAsync();
const event1 = project.getEventById("e1");
console.log("Start Date is :" + event1.startDate);
console.log("End Date is :" + event1.endDate);
const event2 = project.getEventById("e2");
console.log("E2 Start: " + event2.startDate);
console.log("E2 End: " + event2.endDate);

Where is Effort Calculation Code . In Engine And Base Calendar Config is Defined Where .
Why it takes 24 hours per day by dafault .


Post by nickolay »


Post by rahulranjan »

Hi
1.If you see we define hoursPerDay on Calendar Too .

  1. If we want to do for Particular Task

Post by rahulranjan »

rahulranjan wrote: Wed Dec 30, 2020 11:21 am

Hi

  1. For the Below Task (Event1) if i define night calendar the effort for 1 day should be 8 hours but it o/p 24 hours which is default , calendar is not taken into consideration. ? If Duration is 2 then effort should be 2* 8 = 16 hours . It should be based on calendar.
  2. I have defined a calender of 8 hours per day i.e night calendar so if the task duration is 1.
    Start Date is :Tue Dec 01 2020 00:00:00 GMT+0530 (India Standard Time)
    then
    End Date is :Fri Dec 02 2020 00:00:00 GMT+0530 (India Standard Time)
    should be the above
    But it gives
    start Date is :Tue Dec 01 2020 00:00:00 GMT+0530 (India Standard Time)
    End Date is :Fri Dec 04 2020 00:00:00 GMT+0530 (India Standard Time)

Why ?


import { GanttProjectMixin } from "./lib/Engine/quark/model/gantt/GanttProjectMixin.js";

const project = new GanttProjectMixin({
  eventsData: [
    {
      id: "e1",
      name: "Event1",
      startDate: new Date(2020, 11, 1),
      duration: 1,
      calendar: "night",
      manuallyScheduled: false
    },
    {
      id: "e2",
      name: "Event2",
      startDate: new Date(2020, 11, 1),
      duration: 1,
      calendar: "business",
      manuallyScheduled: false
    }
  ],
  calendarsData: [
    {
      id: "general",
      name: "24 Hour Calender",
      intervals: [
        {
          recurrentStartDate: "on Sat at 0:00",
          recurrentEndDate: "on Mon at 0:00",
          isWorking: false
        }
      ],
      expanded: true,
      children: [
        {
          id: "business",
          name: "6 Hour Calender",
          hoursPerDay: 6,
          daysPerWeek: 5,
          daysPerMonth: 20,
          intervals: [
            {
              recurrentStartDate: "every weekday at 12:00",
              recurrentEndDate: "every weekday at 13:00",
              isWorking: false
            },
            {
              recurrentStartDate: "every weekday at 17:00",
              recurrentEndDate: "every weekday at 08:00",
              isWorking: false
            }
          ]
        },
        {
          id: "night",
          name: "Night shift",
          hoursPerDay: 8,
          daysPerWeek: 5,
          daysPerMonth: 20,
          intervals: [
            {
              recurrentStartDate: "every weekday at 6:00",
              recurrentEndDate: "every weekday at 22:00",
              isWorking: false
            }
          ]
        }
      ]
    }
  ],
  dependenciesData: []
});

await project.commitAsync();
const event1 = project.getEventById("e1");
console.log("Start Date is :" + event1.startDate);
console.log("End Date is :" + event1.endDate);
const event2 = project.getEventById("e2");
console.log("E2 Start: " + event2.startDate);
console.log("E2 End: " + event2.endDate);

Where is Effort Calculation Code . In Engine where is Base Calendar Config is Defined Where .
Why it takes 24 hours per day by dafault . - Looking for this too.


Post by nickolay »

Rahulranjan, it is already very hard to understand what you mean, since you formulate yourself very chaotically, but in addition you include random quotations and posts like:

Hi
1.If you see we define hoursPerDay on Calendar Too .

If we want to do for Particular Task

It won't work this way.

Try to be more clear. Ask one question at a time. Formulate yourself clearly (perhaps use a Google translator if your English is not good enough). Do not include random quotations. Help us to help you.

Lets start over. What is your question again?


Post by rahulranjan »

:D :lol: cool

  1. Where in Code Default Calendar Config is Defined ? Enngine
  2. How can we define hoursPerday for Calendar ?

Post by nickolay »

1) Default calendar config? What config exactly you mean? Please point with a link to documentation.
2) You can't. Duration conversion rules are defined globally for the whole project.


Post by nickolay »

Also,
1) Do not uppercase words randomly:

Where in Code Default Calendar Config is Defined ? Enngine

2) Do not insert random words at the end of the sentence.

Where in Code Default Calendar Config is Defined ? Enngine


Post by nickolay »

Regarding the 1), perhaps you mean the calendar config of the project: https://bryntum.com/docs/gantt/engine/classes/_lib_engine_quark_model_gantt_ganttprojectmixin_.ganttprojectmixin.html#calendar

This calendar is used by any task/resource that don't have an explicitly provided calendar.