Maintain start/finish of an activity if in progress or complete

Posted: Thu Jul 22, 2021 7:23 pm
by scscott

I want to understand if it is possible for the engine to "ignore" moving the start date of an activity if it has progress even if the driving predecessor is moved out.

Out of the box the engine will move all downstream activities based on the logic even if the activity has progress.


Re: Maintain start/finish of an activity if in progress or complete

Posted: Fri Jul 23, 2021 7:02 am
by arcady

It's not supported yet. I've made a feature request for this: https://github.com/bryntum/support/issues/3211