In my Scheduler Pro, I have a problem that I don't know how to solve.
This is the following problem: I have the dependencies working normally, but when I change the start and end date of one or any event, it is not changed in the timeline, because they are connected with the dependency. But I want to move my events, do you understand my problem?
If you need I can record a screenshot, thank you very much!
Re: [INFO REQ]
Posted: Tue Nov 22, 2022 4:09 pm
by marcio
Hey filipirafael,
I'm good, hope you doing great too!
We have a demo with dependencies where you changing the start/end date of one event triggers a calculation on other tasks, you can check it here https://bryntum.com/products/schedulerpro/examples/dependencies/
If that's not what you're looking for, a screenshot and a step-by-step about what you want to achieve are more than welcome.