Post by arcady »

Project model has a special config called maxCalendarRange. It limits time range the component iterates when dealing with working time (calculating duration etc.). It's purpose is preventing infinite cycles when working time calendars are misconfigured.

I just see that you combine tasks scheduled in 2018 with new tasks you added in 2025. And I think that config could interfere because its default value is roughly 5 years
If your application is meant to deal with long running tasks please adjust the config accordingly.


Post by ggalipeau »

Ah. That makes sense. We have really long Projects (years). Also explains why you could never reproduce on your side just from my explanation.


Post by arcady »

Yes, I normally experiment with short tasks ..like 1 day duration. It's just easier to calculate. :)