We have integrated advanced Gantt using CRUD manager to sync data and facing issues with baselines sync. Could you please clarify the below question?
Does CRUD Manager supports add/edit/delete for baselines? So for a task, if the baseline is added or modified is it going to Sync? Does the response below look good in that case
Yes, something like this, but without "$PhantomId", baselines has only id. You can review request format after you added new baseline to see data structure.
Yes, something like this, but without "$PhantomId", baselines has only id. You can review request format after you added new baseline to see data structure.
Here is the scenario
I have a Project plan with 5 tasks and baselines dates
I added 2 new tasks and again set baselines for tasks
Triggered Sync
Tasks are getting synced with newly generate ids(CRUD Manager is handling them automatically) but for baselines, how can I get an Id for newly generated baselines as you mentioned we don't have "$PhantomId"
If I pass Id for baselines in response, is it going to automatically replace it with first value in array?