EXPORT TO MSP is not consider duration
Posted: Thu Mar 16, 2023 5:06 pm
by moblitas
Dear Support,
I have tried to export to MSP file but the duration still in zero I have replied into bryntum odoo
https://snipboard.io/RTceYL.jpg
https://snipboard.io/w1oCl5.jpg
Thanks for your support
Milton
Re: EXPORT TO MSP is not consider duration
Posted: Thu Mar 23, 2023 12:34 pm
by arcady
Which version of MS Project do you use? We also need more details on the dataset to reproduce this or steps how this can be reproduced.
Like 1) make a task, 2) assign a resource etc. No need for many tasks I think.
Re: EXPORT TO MSP is not consider duration
Posted: Thu Mar 23, 2023 7:10 pm
by moblitas
Hi,
Currently i am using: Microsoft® Project® Online Desktop Client MSO (Version 2302 Build 16.0.16130.20298) 64-bit
I have used your site to reply that and I have completed the task with duration and resources and it works as I show in the follow link
https://snipboard.io/aiq5vl.jpg
But when I define task without resource and with duration the export option change its as milestines (zero duration) in to MS Project, I think it should be a issue
https://snipboard.io/2akHqz.jpg
https://snipboard.io/3QwIEJ.jpg
Best regards
Re: EXPORT TO MSP is not consider duration
Posted: Fri Mar 24, 2023 6:01 am
by arcady
But when I define task without resource and with duration the export option change its as milestines (zero duration) in to MS Project, I think it should be a issue
Well export feature doesn't change durations itself. It's just MS Project treats the exported data the way it wants.
The data model of the Gantt is a bit different than the MS Project has. And we just don't provide all the data MS Project needs apparently.
So this happens for tasks without assignments - ok. And what scheduling mode do they use? This can be checked on the "Advanced" tab on the task editor.