This is an advanced example of version 5.2.9 on the official website.
I changed the data in the launch-saas file to my data, and then set direction to Backward. At this time, the two data on the interface were different from the actual data.
Support Forum
- Attachments
-
- 屏幕截图 2023-03-21 111620.png (92.54 KiB) Viewed 431 times
-
- 屏幕截图 2023-03-21 111541.png (53.25 KiB) Viewed 431 times
-
- example.zip
- (256.64 KiB) Downloaded 15 times
I set both constraintDate and constraintType in the data to null, but it is still problematic
- Attachments
-
- launch-saas.json
- (50.78 KiB) Downloaded 15 times
Hi,
The task date gets recalculated every time. Please study this guide about task scheduling https://bryntum.com/products/gantt/docs/guide/engine/gantt_events_scheduling
Sorry, my problem is that the data of the start time of these two tasks is different from that displayed on the interface. I'm not doing anything during the data load, nor is there any constraintType or constraintDate in the data.I know the tasks will be rescheduled every time, but why is the start time of these two tasks 2022-10-01
Sorry, my problem is that the data of the start time of these two tasks is different from that displayed on the interface. I'm not doing anything during the data load, nor is there any constraintType or constraintDate in the data.I know the tasks will be rescheduled every time, but why is the start time of these two tasks 2022-10-01
I don't see start dates change to that value.
I've checked the provided file. Loaded it with the advanced demo. I've tried first forward scheduling and then switched the project direction to Backward
mode and the task dates in both cases look this:
I reuploaded my example and you can run it. And the interface in the video is the example I uploaded.Thank you !
- Attachments
-
- example.zip
- (549.22 KiB) Downloaded 15 times
-
- 媒体1.mp4
- (10.68 MiB) Downloaded 17 times