[SchedulerPro] - Get changes from initial scheduling

Posted: Wed Mar 22, 2023 5:19 pm
by guillaume.morin

Hello,

I have a similar case as described here
viewtopic.php?p=111185&hilit=save+load#p111185

I manually call backend to get data and populate scheduler using:

scheduler.project.loadInlineData(remote_data);

The remote data may have inconsistent dates not following constraints, so the scheduler does its magic and reschedule the dependent events.

I'd like this initial scheduling to be saved.
However, after the call to loadInlineData(), scheduler.project.changes is null.

How can I get the initial changes that was applied by the scheduler ?


Re: [SchedulerPro]

Posted: Wed Mar 22, 2023 6:40 pm
by Maxim Gorkovsky

Hello.
Try setting this config to false: https://bryntum.com/products/gantt/docs/api/Gantt/model/ProjectModel#config-silenceInitialCommit
Then changes from the first calculation should be reported as changes


Re: [SchedulerPro]

Posted: Wed Mar 22, 2023 8:39 pm
by guillaume.morin

Gave silenceInitialCommit=false a try, but it now returns a lot of false positive changes.
I included an excerpt of the changes object after initial load.
In summary:

  • events.updated contains all events -> It should not return all events, I will need to investigate, I suspect it is because my load request didn't inlcude an endDate but a only a duration ?

  • resources.updated contains all resources -> I don't see why all resources got updated

  • assignments.added contains all assignments -> make no sense, the scheduler didn't add any assignements

  • dependencies.added contains all dependencies -> make no sense, the scheduler didn't add any dependencies

{
    "events": {
        "updated": [
            {
                "segments": null,
                "effort": 48,
                "constraintType": null,
                "constraintDate": null,
                "endDate": "2023-03-03T00:00:00-05:00",
                "calendar": null,
                "id": "WO-23-001_JOB1"
            }, ...
        ]
    },
    "resources": {
        "updated": [
            {
                "calendar": null,
                "id": "Brassage SLOT 1"
            }, ...
        ]
    },
    "assignments": {
        "added": [
            {
                "units": 100,
                "resourceId": "Brassage SLOT 1",
                "eventId": "WO-23-001_JOB1",
                "$PhantomId": "_generatedn_c2a77166-4328-44bc-ad5a-60181ddf3d54"
            }, ...
        ]
    },
    "dependencies": {
        "added": [
            {
                "type": 0,
                "cls": "",
                "fromSide": null,
                "toSide": null,
                "lag": 0,
                "lagUnit": "day",
                "fromEvent": "WO-23-001_JOB1",
                "toEvent": "WO-23-001_JOB2",
                "active": true,
                "$PhantomId": "_generatedn_396005a5-922c-49fa-8bca-304ed5bebd03"
            }, ...
        ]
    }
}

What I'm looking for is simply to get the list of events for which the scheduling engine changed the start date during initial load.
I guess it will be simpler to keep a copy of the orignal data from server do this comparison myself.


Re: [SchedulerPro]

Posted: Wed Mar 22, 2023 8:52 pm
by mats

events.updated contains all events -> It should not return all events, I will need to investigate, I suspect it is because my load request didn't inlcude an endDate but a only a duration ?

Yes that's likely it.

Can you please post the raw dataset you load and the raw "changes" object so we can have a look?


Re: [SchedulerPro]

Posted: Wed Mar 22, 2023 9:02 pm
by guillaume.morin

Sure thing, see attached.


Re: [SchedulerPro]

Posted: Wed Mar 22, 2023 9:11 pm
by guillaume.morin

FYI, I was able to get the initial changes, without silenceInitialCommit=false, using the following code.
There is really no other change the scheduler can do to my original data, so that will do the job for now.

await this.project.loadInlineData(server_data);

server_data.eventsData.forEach(server_event => {
	let sch_event = this.project.eventStore.getById(server_event.id);
	if (!DateHelper.isEqual(DateHelper.parse(server_event.startDate), sch_event.startDate, "d")) {
		console.log("Initial Schedule change: ", server_event.id, DateHelper.parse(server_event.startDate), sch_event.startDate);
	}
});

Re: [SchedulerPro]

Posted: Wed Mar 22, 2023 9:27 pm
by marcio

Hey guillaume.morin,

Glad that you figure it out and thanks for sharing your solution here in the forums. :)


Re: [SchedulerPro] - Get changes from initial scheduling

Posted: Thu Mar 23, 2023 12:51 am
by guillaume.morin

Just wanted to share my final solution using dataReady event and posting a sync with the changes.

... and ask another question :-)
I didn't find any doc on isInitialCommit, nor on originalData.
Is it ok to use ?

dataReady(e) {
	if (e.isInitialCommit) 
	{
		let updatedEvents = [];
		scheduler.project.events.forEach(x => {
			if (!DateHelper.isEqual(DateHelper.parse(x.originalData.startDate), x.startDate, "d")) 
			{
				updatedEvents.push({
					"id": x.id,
					"startDate": x.startDate,
					"endDate": x.endDate
				});
			}
		});
		if (updatedEvents.length > 0) 
		{
			scheduler.project.sendRequest({
				type: 'sync',
				data: JSON.stringify({
					requestId: scheduler.project.requestId,
					events : {
						updated : updatedEvents
					}
				})
			});
		}
	}
}


Re: [SchedulerPro] - Get changes from initial scheduling

Posted: Thu Mar 23, 2023 9:48 am
by alex.l

Hi, thank you for the question.

You can use isInitialCommit flag, I already updated docs to make it public, the change will be available in the nearest patch release.
Regarding to originalData, it's private and may not work as you expected. originalData object may not contains not committed changes in a record. I see you found that and used in your logic.
But it's for internal use, better to check project.changes to get updated records.