Hello,
Let's say we have 3 dependent events, all done in sequence (default Finish-to-Start):
[Task 1]-->[Task 2]-->[Task 3]
When I first load this in the scheduler, they are all scheduled back to back. - OK
Now if I drag the Task 3 further in the future, it creates a gap with Task 2, and the Task 3 new start date is saved correctly into the backend. - OK
Now if I reload the browser page, the Task 3 is put back right next to Task 2, loosing the manual adjustment that was made by the user.
Is this the expected behaviour ?
How can I keep manual adjustment (creating gap between dependencies) made by the user ?