Is there a config option to only set the baseline for the current index and not previous baseline indexes if these are empty for a task? Post here states about overriding the method:

viewtopic.php?t=19771

Hoping this was just out of the box as it's not expected behaviour when baselining a project.
Many thanks
Paul


Post by alex.l »

Hi Paul,

I've opened a feature request to make that possible. Here is the link to track the status https://github.com/bryntum/support/issues/6825

Thank you!

All the best,
Alex


Post by paul.mather »

Thanks Alex