We have a weird behaviour on the Gantt chart, when two tasks with a dependency are dragged the second one is not being updated, we use https://bryntum.com/products/gantt/examples/advanced/ to reproduce it. the steps are:
- Create a new task "task 1".
- Move the task later than the startDate of the project.
- Create a second task "task2".
- Create a dependency from the end of task1, to the start of task2 with a lag of -5 days.
- Drag task1 in any time from space, then try to move it before the day of the startDate of the task.
- The second task is not being updated.
DEMO:
https://www.loom.com/share/e0de8569c46545229e8fde53b427378a
It looks like when task2 reaches the initial startDate, is not able to move in the past.
Could you please help us on this?