Hello,
We use the 2.0.4 version of Bryntum Gantt.
Steps to reproduce:
1: Create a project
2: Create stages for this project
3: Create multiple tasks with the ending date being the starting date of the next task (examples of task_1 and task_2 in screenshots)
4: Check gantt view
The tasks are displayed on the same day even though they have the right dates on their form view. It happens everytime we set multiple tasks with dates as described above.
Do I need to do something special for this case or is it an issue in the module?
Thanks