Post by kifer »

Hello,

We use the 2.0.4 version of Bryntum Gantt.

Steps to reproduce:
1: Create a project
2: Create stages for this project
3: Create multiple tasks with the ending date being the starting date of the next task (examples of task_1 and task_2 in screenshots)
4: Check gantt view

The tasks are displayed on the same day even though they have the right dates on their form view. It happens everytime we set multiple tasks with dates as described above.

Do I need to do something special for this case or is it an issue in the module?

Thanks

Attachments
task 1 with dates
task 1 with dates
Capture d’écran de 2023-07-10 16-48-53.png (44.48 KiB) Viewed 494 times
task 2: start date = task 1 end date
task 2: start date = task 1 end date
Capture d’écran de 2023-07-10 16-49-03.png (45.21 KiB) Viewed 494 times
both tasks displayed on the same view
both tasks displayed on the same view
Capture d’écran de 2023-07-10 16-49-52.png (45.19 KiB) Viewed 494 times

Post by Terence »

What Odoo version are you on?


Post by Terence »

The fields to edit are planned date. Somehow they are missing in the native Odoo form when they are empty and start- enddate are ignored.

Screenshot 2023-07-11 at 09.10.51.png
Screenshot 2023-07-11 at 09.10.51.png (169.37 KiB) Viewed 472 times

We will look into this.


Post by Terence »


Post Reply