We are having an issue with dispaying many "Auto scheduling" projects in Gantt view
Here my test Case
Icreated 2 projects : Project A and B
Project A Start date : 10/01/2023
Project B Start date : 10/20/2023
I displayed the project A only in Gantt view ==> OK
I displayed the project B only in Gantt view ==> OK
I added Project A to Gantt view and then Project B ==> KO : both project have the same start date and the task of Project B also changed (see attached screenshot)
Expected behaviour : every project keeps his start date
How can I disable auto adjusting dates when I'm displaying more than 1 project?
Support Forum
- Attachments
-
- 2 projects.png (191.33 KiB) Viewed 2569 times
Here is a video from your demo database,
Can you please check As soon as you can?
- Attachments
-
- Odoo - Projects.webm
- (7.59 MiB) Downloaded 141 times
hi,
Thanks for your help I have checked this issue. I have created a GitHub ticket https://github.com/bryntum/odoo-support/issues/128 and we will try to fix this issue in an upcoming version.