The calculation of the finish variance considers non-working days, unlike the MS project that excludes weekends and holidays. For example, the calendar days difference between the days 24/09/2024 to 15/08/2024 is 40
But I want to exclude the weekends, so the finish variance would be 27.
Is there a way to configure it so that it excludes those days and only considers workdays?