Post by wissem »

Hi everyone,

How can i set up the default calendar for one or more projects ?
In Oddo i have set the default working calendar at Standard 38h / week in the général parameters.
When i create a project i have to repeat this calendar manually for each task created in the Gantt view.

Thx


Post by nivl »

We could not reproduce this issue. To assist you with your question, please provide more details including a runnable test case (as described in our support guidelines).

To get the fastest possible support, provide a simple test case based on our standard examples.

Niels


Post by wissem »

Hi,

In attachment you will find the video based on your test environnement in Odoo App store + my environnement.

Attachments
Untitled_ Apr 11 2024 7_20 PM.webm
(15.71 MiB) Downloaded 40 times

Post by nivl »

Hi wissem,

Thank you for the video. We've created a task for this to make this possible.

Niels