[ANGULAR] Resource Utilization – Using a Resource in Multiple Hierarchical Levels
Posted: Fri Aug 29, 2025 2:26 pm
by pfund
Hello,
I am currently working with the Resource Utilization component and would like to assign the same resource across multiple hierarchical levels. However, when I try to configure it this way, I receive an “Id Collision” error.
Could you please clarify whether it is supported to include the same resource in different hierarchy levels? And if so, what would be the correct approach to configure this without running into ID conflicts?
Thank you in advance for your support.
Best regards
Re: [ANGULAR] Resource Utilization – Using a Resource in Multiple Hierarchical Levels
Posted: Fri Aug 29, 2025 4:22 pm
by alex.l
Hi,
Please explain your logic a bit, what did you mean by "assign the same resource across multiple hierarchical levels"? Histogram shows tasks grouped by resource, how should it looks like in your version?
Did you see our guide https://bryntum.com/products/gantt/docs/guide/SchedulerPro/resourceviews/resourceutilization ? It might give you some inspiration how it works.
Re: [ANGULAR] Resource Utilization – Using a Resource in Multiple Hierarchical Levels
Posted: Mon Sep 08, 2025 9:42 am
by pfund
We would like to assign the same resource to different teams, so that it appears multiple times in the resource utilization view depending on the team context. I’ve attached a screen design showing the resource current.user included twice.
Re: [ANGULAR] Resource Utilization – Using a Resource in Multiple Hierarchical Levels