Hi Team,
My subscription has ended, so I’m currently using a different login to continue this discussion. We will be renewing the forum subscription soon. In the meantime, I’ll continue the conversation here.
As mentioned in my earlier post, I was having difficulty identifying the correct EF and LF values. Now I am clear about the Early Finish (EF) value, which corresponds to the task’s planned finish date. However, I am still facing some confusion regarding the Late Finish (LF) value used in the slack calculation.
According to the documentation, the calculation should be:
LF: 15-Mar-2026 13:28:18 (Project finish date)
EF: 04-Jan-2026 23:27:49 (Planned finish)
Slack = LF − EF ≈ 69 days.
However, when I log the slack values in the system, it is showing 18.6 days, and you also mentioned 18.6 days earlier.
Could you please clarify which task date is being considered for calculating this 18.6-day slack value?
Attached respective forum link and screenshot for reference.
viewtopic.php?t=34844&start=10
Thanks,
Hema Gopisetty