Hi,
I managed to reproduce a bug in the https://bryntum.com/products/gantt/examples/resourceutilization/
const gantt = new Gantt({
project,
dependencyIdField : 'sequenceNumber',
resourceImagePath : '../_shared/images/transparent-users/',
appendTo : 'container',
collapsible : true,
header : false,
minHeight : 0,
viewPreset : 'weekAndDay',
tickSize : 40,
columnLines : true,
startDate : '2024-01-16',
columns : [
{ type : 'name', width : 280 },
{ type : 'SchedulingDirection', width : 280 },
{ type : 'schedulingmodecolumn', width : 280 },
{ type : 'predecessor', width : 280 },
{ type : 'resourceassignment', showAvatars : true, width : 170 }
]
});
Steps to repro:
Set task Report to managment with backward direction, fixed effort and a predecessor, in this case task 5
Set Gather documents task to scheduling direction Backwards, with a predecessor in this case task 4
Try to change scheduling mode from Gather documents task to fixed effort
Pop up A cycle has been found, formed by: "Gather documents" -> "Gather documents" but can't do nothing
Is this the intended behaviour?
Thanks,