Hi,
I found a bug with fixed effort scheduling mode, it can be reproduced in bryntum site: https://bryntum.com/products/gantt/examples/resourceutilization/.
const gantt = new Gantt({
project,
dependencyIdField : 'sequenceNumber',
resourceImagePath : '../_shared/images/transparent-users/',
appendTo : 'container',
collapsible : true,
header : false,
minHeight : 0,
viewPreset : 'weekAndDay',
tickSize : 40,
columnLines : true,
startDate : '2024-01-16',
columns : [
{ type : 'name', width : 280 },
{ type : 'schedulingmodecolumn', width : 280 },
{ type : 'duration', width : 150 },
{ type : 'effort', width : 150 },
{ type : 'resourceassignment', showAvatars : true, width : 170 }
]
});
Steps to repro:
create a new task
set mode to "Fixed Effort"
set effort to 40 hours
set duration to 5 days
open resource picker and assign 2 resources, one with 90% units and the other one with 60%, save it
Result: duration is set to 0 without reason.
See attached video on how to repro in your demo site mentioned above. Again, this to me is a Blocker bug, it removes user data and has to be set it again, also it can be dangerous when we load the project and computations...
Please set it as top priority, several customers on our side are afected.
Thanks,